Chapter Living Construction Notice Update

Dear neighbours,

 This weekend we were scheduled to increase the height of our tower crane on the Weston Street elevation, however due to unexpectedly high winds on Sunday the crane team involved were only able to install two of the four planned mast sections.

We are now reviewing the availability of crane adaption teams and liaising with statutory authorities to organise the installation of the remaining two mast sections. Once confirmed we will update via the usual communications channels accordingly.

Many thanks for your continued patience with ongoing works.

 

Notification 10.06.24